Yes and no. The site of The Gathering at South Forsyth, at Union Hill Road and Ronald Reagan Boulevard next to GA 400, is being graded under a county clearing and grading permit issued July 31, 2026. No building permit and no site development permit has been filed, and the arena still has no NHL team.
That distinction matters, because grading is the cheapest and most reversible part of a project like this. Below is what Forsyth County’s own records show, what the approved zoning allows, and what has to happen before anything goes vertical. We first covered the project in 2026 Projects to Watch. This is where it stands now.
What the county permit actually covers
The permit is CG260010, a Clearing and Grading plan in the county’s online permit system, project name “The Gathering at South Forsyth, Mass Grading,” at 1445 Union Hill Road.
| Item | What the county record shows |
|---|---|
| Permit type | Clearing and Grading |
| Applied | June 5, 2026 |
| Issued | July 31, 2026 |
| Plan status | Approved, county review 100 percent complete |
| Total acreage | 88.13 acres |
| Disturbed acreage | 75.38 acres |
| Parcels covered | 16 |
| Main parcel | 043 022, 1445 Union Hill Road, 36.74 acres, zoned CBD |
| Owner and developer listed | Krause Entertainment, Vernon Krause |
| Permit expires | June 5, 2027 |
| Inspections logged | One, an arborist site walk on July 14, 2026 |
The plan did not sail through. County engineering marked it not passed three times, on June 16, July 15 and July 24, before passing it on July 28. That is normal for a site this size, and it tells you the county reviewed it closely.
What the permit does not cover is anything you would recognize as a building. A clearing and grading permit lets a contractor clear trees, move dirt and set erosion control. Roads, utilities, parking and pads come under a separate site development permit, and in the county system that permit is still listed as not yet applied for. When it shows up, that is the real signal.
The timeline the developer has given
Krause Sports and Entertainment said in early September that grading would start September 7, 2026, run about five months, and be followed by utility and electrical work, with vertical construction planned for summer 2027. Five months from early September puts the end of grading around February 2027.
The land itself has been in the developer’s hands for years. Gathering at South Forsyth LLC bought the core tract on August 30, 2022 from Pope and Land Union Hill LP in a $52,000,000 multi parcel sale, according to the Forsyth County Board of Assessors.
What the approved zoning allows
The site sits in the Ronald Reagan/Union Hill Overlay District, a 164 acre overlay the Board of Commissioners first adopted in 2008 and rewrote on January 9, 2025 for this project. The current code, Chapter 21, Article IX of the Unified Development Code, does three things that matter.
It caps the apartments. Multi family units in the main subarea cannot exceed 1,800.
It hands the phasing to the deal documents. The code says the property shall be developed in phases as set out in the county’s March 26, 2024 memorandum of understanding with the developer, and that a development agreement approved by the commissioners governs where the two conflict. That development agreement had to be approved before the county could issue any land disturbance permit in the main subarea, which is why the June 2025 approvals came before this grading permit.
It allows a multi purpose arena, offices, retail, hotels and parking decks up to eight levels, along with everything the underlying CBD commercial district allows.
The phasing itself comes from the definitive documents the county, the school board and the Development Authority approved on June 11, 2025. The county’s own presentation that night put the full program at 1.6 million square feet of office and retail, 700,000 square feet of arena space seating 18,500, two to five hotels totaling 500 rooms, a 15,000 square foot building for a fire station and sheriff’s precinct, 1.2 miles of greenway trail, 1,800 multi family units of one and two bedrooms, and 150 detached single family homes. It laid the phases out this way:
| Phase | What it includes | The condition attached |
|---|---|---|
| Phase 1 | 600 apartments, 200,000 to 300,000 square feet of office, 300,000 to 400,000 square feet of retail, one hotel of 120 to 150 rooms, a sheriff and fire station, the 18,500 seat arena and two parking decks | No certificate of occupancy for the Phase 1 apartments until the office and retail have theirs |
| Phase 2 | 600 apartments, 250,000 to 350,000 square feet of office, 200,000 to 300,000 square feet of retail, two hotels of 250 to 350 rooms | No certificate of occupancy for the Phase 2 apartments until the arena is 50 percent built |
| Phase 3 | 200,000 to 300,000 square feet of office | Phase 2 must be complete first |
| Phase 4 | 600 apartments | Phase 3 must be complete first |
Every phase has to be finished before the next one can start. In plain terms, nobody moves into an apartment at The Gathering until the commercial space around it is open, and the second wave of apartments is tied directly to the arena.
Where the money stands
The county’s money is tied to hockey. Forsyth County agreed to back $225 million in bonds, issued through the Development Authority and repaid from a tax allocation district voters approved 56 to 44 in November 2024. But the bonds only happen if an NHL team comes. County Manager David McKee put it simply at the June 2025 meeting: “No NHL, no bond.”
Vernon Krause has been just as direct about the arena. Asked in June 2025 whether he would build it without a team, he said no, that his group would only build an arena if awarded an NHL franchise, and that without one he would have to reassess.
Where the NHL stands
The league has not awarded a team to Georgia. In September 2026, NHL Deputy Commissioner Bill Daly said metro Atlanta was not close to an application phase and that the league was looking at Houston and Austin. Krause said the same week that the NHL had made no decisions on the project.
The Gathering is also not the only Atlanta bid. An Alpharetta group is pitching the North Point Mall site six miles south, and a third group led by former NHL player Anson Carter launched in September. If the league does come back to Atlanta, Forsyth County is competing for it.
What happens if there is no NHL team
This is the question nobody has answered in plain terms, so here is what the approved documents say.
Under the county’s summary of the deal, the arena is a Phase 1 component, and nothing in Phases 2, 3 or 4 can begin until Phase 1 is complete. Read together with Krause’s own statement that there is no arena without a team, the approved plan without the NHL tops out at Phase 1: office, retail, a hotel and up to 600 apartments, with no one living in those apartments until the office and retail are open. The remaining 1,200 apartments are locked behind an arena that does not get built.
And that Phase 1 would have to be financed without the $225 million county bond.
Anything beyond that would take a new deal or a change to the zoning, and either one goes back in front of the Board of Commissioners in public. We have not seen the full development agreement, only the county’s presentation of it, so treat this as our reading of the public record rather than the final word.
What it means if you own land around Union Hill Road
Our read, which is ours and not the county’s.
Price on the zoning, not the hockey. The overlay, the commercial zoning and the road work around this site are real and approved. An NHL team is not. Land within a few miles of Union Hill Road and McGinnis Ferry carries value today because of GA 400 access, the McGinnis Ferry widening and the commercial entitlement already in place. Anyone pricing nearby land as if an arena and 18,000 fans a night are a sure thing is ahead of the facts.
Grading is not a commitment. A mass grading permit is the cheapest step in a $3 billion project, and it keeps the developer’s approvals moving. The commitment shows up as a site development permit, then building permits, then a financing announcement. Watch for those, in that order.
The roads are coming either way. McGinnis Ferry Road phase 1 is under construction toward a spring 2028 finish, phase 2 from Union Hill Road to Douglas Road is in design, and the GA 400 express lanes run north to just past McFarland Parkway. Those projects change access to this part of the county whether or not a puck ever drops. We track them in What Is Under Construction in Cumming and Forsyth County?
We will update this post when the site development permit is filed or the NHL makes a decision, whichever comes first.
Frequently asked questions
Is The Gathering at South Forsyth under construction?
The site is being graded under a Forsyth County clearing and grading permit, CG260010, issued July 31, 2026 for 75.38 disturbed acres. No site development permit or building permit has been filed, so nothing vertical is under construction yet.
When will The Gathering at South Forsyth open?
There is no opening date. The developer has said grading will take about five months from September 7, 2026, followed by utility work, with vertical construction planned for summer 2027. The arena depends on the NHL awarding a team, which has not happened.
Where is The Gathering at South Forsyth?
At Union Hill Road and Ronald Reagan Boulevard along GA 400 in south Forsyth County, with a permit address of 1445 Union Hill Road. It sits inside the Ronald Reagan/Union Hill Overlay District.
What is being built at Union Hill Road and Ronald Reagan Boulevard?
The approved plan calls for up to 1,800 apartments, 150 detached single family homes, 1.6 million square feet of office and retail, hotels totaling about 500 rooms, a fire station and sheriff’s precinct, parking decks and an 18,500 seat arena, built in four phases. Right now the only permitted work is clearing and grading.
Is an NHL team coming to Forsyth County?
Not yet. The NHL has not awarded a franchise to Georgia, and in September 2026 Deputy Commissioner Bill Daly said metro Atlanta was not close to an application phase. Forsyth County and an Alpharetta group are both pursuing a team.
What happens to The Gathering if there is no NHL team?
The county’s $225 million bond is only issued if a team comes. Under the county’s summary of the approved deal, the arena is part of Phase 1 and later phases cannot start until Phase 1 is complete, so without an arena the approved plan is limited to Phase 1: office, retail, a hotel and up to 600 apartments.
Sources
Forsyth County Customer Self Service portal, plan CG260010, The Gathering at South Forsyth, Mass Grading, read November 19, 2026: https://css.forsythco.com/EnerGov_Prod/SelfService#/plan/64bab154-130a-4f98-bb06-b8c23dbca4f0
Forsyth County Board of Assessors, parcel 043 022, 1445 Union Hill Road, owner and sales history, read November 19, 2026: https://beacon.schneidercorp.com/Application.aspx?AppID=1027&LayerID=21667&PageTypeID=4&PageID=9230&KeyValue=043%20%20%20022
Forsyth County Unified Development Code, Chapter 21, Article IX, Ronald Reagan/Union Hill Overlay District, version of October 1, 2026: https://www.forsythco.com/udc-complete/
Forsyth County, The Gathering at South Forsyth, Presentation of Definitive Documents, June 11, 2025: https://forsythco.b-cdn.net/app/uploads/2026/09/06-10-25-Gathering-Arena-Agreement-presentation-PDF.pdf
Forsyth County News, “The Gathering at South Forsyth is closer to going vertical amid renewed talk about the NHL,” September 4, 2026: https://www.forsythnews.com/news/growth-development/the-gathering-at-south-forsyth-is-closer-to-going-vertical-amid-renewed-talk-about-the-nhl-heres-whats-happening/
Forsyth County News, commissioners’ vote on the Ronald Reagan/Union Hill overlay, January 9, 2025: https://www.forsythnews.com/news/government/hockey-legend-attends-commissioners-vote-on-the-gathering-at-south-forsyth-what-does-that-mean-for-focos-chances-of-getting-an-nhl-team/
FOX 5 Atlanta, Forsyth County greenlights the development and the final agreements, June 2025: https://www.fox5atlanta.com/news/gathering-south-forsyth-nhl-team-development-meeting
FOX 5 Atlanta, developer clarifies the NHL status for the arena, September 4, 2026: https://www.fox5atlanta.com/news/developers-claim-funding-is-secured-massive-nhl-arena-forsyth-county
Atlanta News First, site work to begin on the entertainment hub and arena, September 4, 2026: https://www.atlantanewsfirst.com/2026/09/04/site-work-begin-entertainment-hub-arena-forsyth-county-developer-says/
Atlanta Journal-Constitution, a third Atlanta NHL bid, September 2026: https://www.ajc.com/business/2026/09/atlanta-nhl-hopes-get-third-bid-as-anson-carter-breaks-away/
Crawford Lands, LLC is a licensed real estate brokerage in the State of Georgia, license #81852. This article is general information, not legal, tax or appraisal advice. Permits, zoning, agreements and schedules change; confirm anything you rely on with Forsyth County before you act on it. Contact us.
Own land near where Forsyth County is growing? Start with what it is worth.
Or get the Forsyth County land sales and zoning reports by email: sign up here.